Weeks 12-15: Interior Finishing

As week 12 gets underway we have a host of finishing trades booked in over the coming weeks.

And it is all go...

First up is the joinery measure and installation of the bespoke kitchen and laundry cabinetry.

Floor layer installs the German-engineered Haro flooring.

Tiler completes the waterproofing and then tiling to the bathrooms and kitchen.

Plumber fits off the showers and tapware.

Fire installer fits the Jayline ULEB (Ultra Low Emmision Burner) log fire

Carpets are fitted to the bedrooms

Exposed aggregate concret driveway is completed

Electrician fits the switches and sockets.